What a heat pump installation actually involves
A typical UK heat pump install takes 2–5 working days on-site, plus 2–6 weeks beforehand for survey, design and grant processing. Here's the sequence, what a good installer does at each stage, and what disruption to expect at home.
Week 0: enquiry & initial conversation
- You contact 2–3 MCS-certified, BUS-registered installers.
- They ask about property type, age, insulation, current heating, and rough number of radiators.
- A good installer doesn't quote at this stage — they ask to survey.
Weeks 1–2: site survey
This is the most important stage. A proper MCS heat-loss survey is 2–4 hours on-site, measuring:
- Each room's floor area, window area, and existing radiator output.
- Wall construction (solid brick, cavity, timber-frame) and insulation state.
- Loft insulation depth and condition.
- Existing pipework (microbore, 22 mm, 28 mm) — this affects whether pipework needs upgrading.
- Outdoor unit location options and condensate drain routing.
- Hot water cylinder location.
- Electrical supply: consumer unit capacity and the main fuse rating (often a stumbling block).
Weeks 2–4: design and quote
The installer sends a written design pack including:
- Total heat loss in kW.
- Specified heat pump model and kW output.
- Designed flow temperature.
- Estimated SCOP.
- Radiators to be replaced (room by room).
- Hot water cylinder size and brand.
- Itemised quote with BUS grant deduction clearly shown.
Weeks 4–6: BUS voucher and contract
- The installer applies to Ofgem for a Boiler Upgrade Scheme voucher.
- Voucher issued (typically 1–2 weeks).
- You sign the contract with a small deposit (10–20% is normal).
- Installation date confirmed, typically 4–10 weeks out depending on the installer's diary and equipment lead times.
Day 1 on-site: prep and outdoor unit
- Installers arrive (typically 2 engineers).
- Outdoor unit position confirmed and base prepared (concrete plinth or wall brackets).
- Outdoor unit delivered, lifted into place, levelled.
- Refrigerant pipework routed to the indoor location, drilling 1–2 wall penetrations.
- Condensate drain routed to a downpipe or soakaway.
Day 2: indoor plumbing and cylinder
- Old hot water cylinder removed if applicable. Combi boiler isolated (or removed if you're going full electric).
- New unvented cylinder installed.
- Heat pump heat exchanger and buffer connected.
- Hot water mains pressure tested.
- System filled, vented, flushed.
Day 3: radiator changes and electrical
- Identified radiators replaced (usually 1–3, sometimes none).
- Smart thermostat and weather-compensation sensor installed.
- Electrical works: dedicated heat pump circuit, isolators, possibly a consumer unit upgrade.
Day 4: commissioning and handover
- System started and run through manufacturer commissioning procedure.
- Flow temperature set, weather compensation curve adjusted.
- SCOP verified against design.
- Installer walks you through controls.
- MCS certificate issued.
- Building Control notification submitted (if required).
- Manufacturer warranty registered.
What disruption to expect at home
- No heating for a few hours during cylinder swap on day 2.
- No hot water for half a day on day 2.
- Outdoor noise while drilling and craning the outdoor unit.
- Indoor mess in the rooms with radiator changes — installers should sheet up.
- Electrical disruption for 1–2 hours if the consumer unit is being upgraded.
What "fully commissioned" should mean
By the end of day 4 you should receive:
- MCS certificate (PDF and original on paper).
- Manufacturer commissioning report.
- Heat-loss survey and design pack.
- Warranty registration confirmations.
- Quick-start guide for the controls.
- Annual servicing booking for ~12 months out.
Common things that go wrong (and aren't deal-breakers)
- Refrigerant leak during commissioning. Caught at install. Installer fixes and re-charges.
- Flow temperature too high on day 4. Comes down as the installer dials in weather compensation over the first cold week.
- One room slow to heat. Usually a balancing issue — fixed without parts.
- Cylinder noise. Air in the system; bleeds out over a week.
Find your installer
Start with our regional directory and use the questions to ask guide.